Construction of the 5,000 square foot Hunterdon Central Regional High School Storage Building was ground up, slab on grade engineered metal building. The building included new electric, sewer, and water services that were all brought to the building pad by DeSapio Construction, Inc. The project also included construction of a new parking lot, demolition of existing temporary classroom units and a new storm water management system. Construction was completed in 6 months and within budget. The building is used for storage for the HCRHS Buildings and Ground Department.
Project Type: General Construction
Completed: January 2023
Contract Amount: $1,699,000.00
Owner: Hunterdon Central High School (84 State Route 31, Flemington, NJ)
Completed: January 2023
Contract Amount: $1,699,000.00